Thailand · Warehouse
Logistics Warehouse, 12,000 m²
Distribution center for a Thai consumer-goods group near Bangkok Port, erected in 62 days including two internal mezzanine office blocks.
- Location
- Thailand
- Completed
- 2024
- Area
- 12,000 m²
- Clear span
- 32 m
- Steel tonnage
- 780 t
The client needed a cross-dock distribution center within 90 days of groundbreaking. We engineered 32 m clear-span rigid frames with 8 m eave height, 12 dock levelers and a 1,200 m² mezzanine office block, then shipped 780 t of fabricated steel in nine 40'HC containers.
Our six-person erection supervision team worked alongside local crews, completing the frame in 38 days and full handover — cladding, doors, floors and offices — on day 62.